Complete fictional sample plan
FICTIONAL SAMPLE - 12 x 10 bedroom flooring and paint
Combined project · 120 sq ft floor · 320 sq ft net walls
Quantities & materials
7 boxs · $45.00 each
120 sq ft × 1.1 ÷ 20 sq ft/box, rounded up
2 gallons · $38.00 each
320 sq ft × 2 coats ÷ 350 sq ft/gallon, rounded up
1 gallon · $32.00 each
3 pieces · $14.00 each
1 piece · $30.00 each
1 kit · $18.00 each
1 kit · $24.00 each
1 kit · $28.00 each
1 kit · $16.00 each
1 allowance · $40.00 each
Budget breakdown
Before you buy
- Confirm room dimensions and subtract door/window openings once.
- Obtain local supplier prices, product coverage and full box quantities.
- Check delivery dates, return policies and access for materials.
- Confirm permissions, permits and licensed-trade needs before work.
- Check subfloor condition, moisture, underlayment, transitions and trim.
- Confirm flooring layout, product acclimation and manufacturer waste guidance.
- Check primer needs, surface repairs, tape, covers, rollers, brushes and cleanup supplies.
- Use the paint label coverage for your surface; primer is a separate material.
Suggested work sequence
- Measure the space and record existing conditions.
- Set the scope, obtain quotes and confirm permissions or permits.
- Order materials and coordinate deliveries and trade availability.
- Protect retained items and arrange appropriate removal and disposal.
- Prepare and repair surfaces following the selected product instructions.
- Complete planned paint preparation, primer where needed and finish coats; allow specified drying time.
- Install flooring, transitions and trim in the sequence required by the manufacturer and scope.
- Install remaining fittings, inspect completed work and resolve punch-list items.
- Clean up, record actual costs and save receipts and warranty details.
Assumptions to verify
- FICTIONAL SAMPLE: illustrative prices only, not a quote or a customer project. Room 12 x 10 x 8 ft; openings 32 sq ft; ceiling excluded. Waste 10%; flooring coverage 20 sq ft/box; paint 350 sq ft/gallon, two coats. Tax 6% of listed materials; contingency 15%. No actual costs recorded.
- Rectangular room; feet and square feet. Automatic quantities do not model irregular room shapes; enter separately measured materials and verify them before purchase.
- Quantities are estimates from your measurements, not a site survey. Verify product coverage, pattern waste, substrate and fit.
- Budget uses your prices and allowances, not local quotes. Unpriced items are excluded, not free. Labor, permits and delivery need your estimates.
- Planning worksheet only; not construction drawings, a contractor quote or code approval. Materials, labor and the plan purchase fee are separate.
Your notes
FICTIONAL EXAMPLE: all prices, allowances and conditions are illustrative, not supplier or contractor quotes. Scope: replace carpet with floating flooring and repaint bedroom walls. Room 12 x 10 ft, walls 8 ft high. One 3 x 7 ft doorway and one 11 sq ft window total 32 sq ft of openings. Ceiling, closet and adjacent rooms excluded. Floor: 120 sq ft plus 10% waste = 132 sq ft; seven 20 sq ft boxes provide 140 sq ft. Selected fictional flooring has an attached pad; separate underlayment is excluded, subject to product and subfloor requirements. Paint: 352 sq ft gross walls minus 32 sq ft openings = 320 sq ft; two coats cover 640 sq ft. At 350 sq ft/gallon, buy two gallons. One gallon of primer assumes at least 320 sq ft coverage for one coat. Trim paint is already on hand. Trim: 44 ft perimeter minus 3 ft doorway = 41 ft; three 16 ft lengths provide 48 ft before cuts. Verify lengths against layout. Existing subfloor is assumed dry, sound and level; no structural, plumbing or electrical changes. Tools are owned or borrowed. Add repair, rental or extra product costs if needed. Labor $400 and delivery $35 are placeholders to replace with quotes. Permit allowance is $0 only for this fictional scope; confirm local requirements. Tax is an illustrative 6% of listed materials and supplies only; taxable services and disposal treatment vary. Contingency is 15% of materials, tax and allowances. Planner purchase fee is separate. No materials have been purchased and no actual costs are entered. After purchase, your own plan lets you update measurements, prices and acquired items, save changes and export again.